Every construction or drilling investment involves interference with the natural environment.
Our primary goal is for the investments to have the least possible impact on the natural environment. In the case of investments, it is necessary to prepare the construction site/drilling rig for the future investment for the stable installation of the drilling rig and the necessary equipment.
We carry out investments in compliance with the highest standards and environmental protection regulations.
Preparatory works are carried out by TRANS-WIERT S.A.:
1. Entering the area, mowing grass, cutting down trees and shrubs, grubbing up stumps.

2. Removing the humus and collecting it in heaps around the construction site (The collected humus and topsoil are used at the final stage of construction to restore the investment site to its original condition).
3. Levelling the terrain to the required level.
4. Soil replacement (carried out if necessary, in the case of unstable ground).

5. Securing the site with a geo-membrane/PEHD foil (protections are used to protect the ground and underground water from contamination).

6. Laying concrete slabs on a sand bed.

7. Construction of tanks for water from test pumping from the borehole (the tanks are also protected with foil to prevent the collected mud/water from penetrating the ground and aquifers).

8. Fencing of the construction site and tanks, including the installation of a protective net against the migration of amphibians (In order to maintain safety, the drilling site is secured against access by unauthorized persons, while in order to protect amphibians and small animals, special herpetological nets are installed to prevent the movement of amphibians into the drilling area).

9. Dismantling and stacking of slabs (after the investment is completed, the machines and devices, slabs and layers protecting the ground are dismantled).
10. Land reclamation (Reclamation is the last and equally important stage of the Investment. We carry out land reclamation, restoring the investment areas to their original condition. In order to restore the utility value and landscape values of a given area, agrotechnical works are carried out, including soil fertilization and sowing of grass mixtures and planting of tall vegetation, trees and shrubs, in accordance with the requirements of the Specification of Order Conditions and the assumptions included in the Mining Plant Operation Plan).